Tuesday, April 15, 2008

Remodel Update Week 2

End of Day 6 - Concrete forms done
















End of Day 7 - Concrete poured






















End of Day 8 - Concrete forms off. Windows and internal walls framed.

















End of Day 9 - More walls and windows framed. Floor patched.
















End of Day 10 - Windows & internal walls framing mostly done.

















End of Day 11 (yes, they worked on Saturday) - 2nd floor joists delivered

















The front driveway = lumber yard.